Fina Phase construction has been approved on the SCHEELS Tiger Performance Center! Thank you to all our donors! Anticipated opening - late Fall 2026

Each year Tiger Athletics and Activities supports nearly 2,200 Cedar Falls District students in athletics, fine and performing arts, and STEM. The Tiger Performance Center represents the future of our programs for the next fifty years and is estimated to impact over 85,000 future Elite Tigers.

Photos from Tiger Performance Center's post 10/01/2026

We had a sneak peek of the CF Scheels Tiger Performance Center with a few guests today! Walls painted, indoor graphics applied, basketball hoops and scoreboard up! In the coming weeks, signage, various netting with final flooring (track, turf and multi-purpose) in about 1 month!

Located between the main high school building and stadium, the TPC will offer almost 44,000 ft² of indoor academic and activity space.

Thank you to the many generous donors and our volunteer fundraising committee!

THIS. IS. Tiger Country!

08/21/2026

POV: Equipment has been been removed, temporary fencing and grass seed spread. One more step towards facility completion!

School starts Monday!

08/12/2026

Blue skies over the CF Scheels Tiger Performance Center.

Located between the main high school building and stadium, the TPC will offer almost 44,000 ft² of indoor academic and activity space.

Thanks to Peters Construction Corporation, we are on our way to completion by late November! Thank you to the many individual and business donors who have supported this project!

Learn more about the project at: https://tigerperformancecenter.com/

07/09/2026

July picture update! Construction remains on track for late Fall 2026 opening! Thank you to all our donors!

THIS. IS. Tiger Country!

05/22/2026

S/O to this TPC fundraising team who gathered to celebrate the final approval to complete the facility! Thank you to these dedicated volunteers!

L-R, front row: Bethany Benner, Lindsay Cota, Troy Becker, Joyce Coil
L-R, back row: Susie Hines, Chad Rinehart, Summer Meyer, Ryan Kriener, Sam Wingert, Janelle Darst

Photos from Tiger Performance Center's post 04/28/2026

Every day - one step closer with Final Phase approved!

04/28/2026

The FINAL PHASE bid has been approved for the SCHEELS Tiger Performance Center by the Cedar Falls Community School District Board of Education on Friday, April 27, 2026.

The $3.268M bid by Peters Construction of Waterloo was accepted. The phase 2 final bid will include paint, HVAC, lightning, signs/graphics, overhead doors, accessories and flooring. We are incredibly grateful for the many donors who have supported this project and to the dedicated fundraising committee!

Construction will continue on the facility with anticipated opening in late 2026/early 2027!

Photos from Tiger Performance Center's post 04/14/2026

After the public hearing for the SCHEELS Tiger Performance Center last evening, the BOE heard and approved the Phase 2 completion steps in proposed plans and specifications. Interior, exterior and MEPT (mechancial, electrical, plumbing, technology) were outlined.

Final details and construction costs will be received at the April 20 meeting.

Thank you to our community of supporters including our volunteer fundraising committee, CF Scheels, Martin Bros. Distributing, and the many, many business and individual donors!

03/10/2026

At last night's BOE meeting (March 9), the Board set a public hearing for April 13 for PHASE 2 COMPLETION of the SCHEELS Tiger Performance Center. At the April meeting, after the TPC public hearing and within the regular agenda - the completion steps will be shared on the project.

Thank you to the many donors - individuals, grantors and corporations; to CF Scheels for taking the lead; and to the dedicated TPC Fundraising Committee.

Your investment is more than a building — it is an investment in opportunity, growth, teamwork, and excellence for every student who walks through those doors. We are deeply grateful for your partnership in bringing this vision to life.

03/06/2026

A quick snapshot of the SCHEELS Tiger Performance Center - between the rain drops - and we've got exciting next steps with Phase 2 information to be presented at the Board of Education meeting on Monday, March 9.

Want your school to be the top-listed School/college in Cedar Falls?
Click here to claim your Sponsored Listing.

Category

Address


2701 W 27th St.
Cedar Falls, IA
50613

Alerts

Be the first to know and let us send you an email when Tiger Performance Center posts news and promotions. Your email address will not be used for any other purpose, and you can unsubscribe at any time.

Subscribe

We will notify you when anything happens in Cedar Falls.