Uable
Renewable Energy : Biomass & Waste
Solar Power & Energy Management System (EMS)
14/02/2025
Assembly work, new steam turbine 26MW progress ahead the Plan. Next milestone are installing of Reduction Gear & Moving the Existing Generator, Welcome 600ton Crawler Crane at the end of Feb.
02/01/2025
Ready for Installation, unloading completed, fabrication support work in progress, our best effort output for royalty Client.
19/11/2024
Construction progress for Waste Bunker and Boiler area of Chiangmai Waste to Energy 9.9MWe, this project will manage MSW for 200,000 tons/annual.
02/11/2024
Coming soon 26MW replacement project, FAT JAPAN.
11/10/2023
Thank you for giving us with the opportunity to proudly be a part of the challenging 26MWe steam turbine and generator replacement project.
08/05/2023
https://www.meed.com/abu-dhabi-opens-waste-to-energy-bids
Abu Dhabi-based Emirates Water & Electricity Company (EWEC) and the Abu Dhabi Centre for Waste Management (TEDWEER) have opened the bid received on 14 APR for the contract to develop Abu Dhabi's 1st Waste-to-Energy (WtE) project.
JAPAN's Marubeni Corporation, Hitachi Zosen Inova (Switzerland) and JOIN submit the lowest bid for the Contract 😁
(Other is France's Suez)
We are proud to be part of this enormous project.
The WtE Plant designed capacity of 900,000 tones of waste a year. It will be the world’s largest thermal treatment.
คลิกที่นี่เพื่อเป็นสมาชิก?
ติดต่อ ธุรกิจของเรา
เบอร์โทรศัพท์
ที่อยู่
OCC/One City Centre
Bangkok
50300