Progress Update of Ariya Vihara Building Project
https://ariyavihara.org/ariya-vihara-building-project/

Dhammapada verse 122

One should not think lightly of doing good, imagining 'A little will not affect me'; just as a water-jar is filled up by falling drops of rain, so also, the wise one is filled up with merit, by accumulating it little by little.
莫輕視善行,以為「小善不會為我帶來果報」;如同滴水能注滿水瓶,智者累積小善至福德滿盈。
法句經 偈頌次 122

Photos from Ariya Vihara Building Project's post 28/04/2026

Casting of the Sīmā Hall columns is in progress.

Photos from Ariya Vihara Building Project's post 28/04/2026

Slab casting of the lower ground floor is completed.

Continuing the Journey - Ariya Vihara Building Project 16/04/2026

Continuing the Journey - Ariya Vihara Building Project The video shows the progress of the Ariya Vihara Building Project up to April 2026. Video by Sis. Wendy Khaw and Zense

Photos from Ariya Vihara Building Project's post 08/04/2026

Rebar works installation, backfilling and compaction of earth at lower ground slab are in progress.

Photos from Ariya Vihara Building Project's post 31/03/2026

Formworks, rebar modifications and lean concreting are in progress.

Photos from Ariya Vihara Building Project's post 05/03/2026

Formwork and installation of PC Strand are in progress at lower ground

Photos from Ariya Vihara Building Project's post 03/02/2026
Photos from Ariya Vihara Building Project's post 16/01/2026

Lower ground beam formwork works are in progress.

Photos from Ariya Vihara Building Project's post 08/01/2026

Sīmā Hall pilecaps' concreting has been completed. Concreting of other pilecaps are in progress.

Photos from Ariya Vihara Building Project's post 02/01/2026

We are happy to share that the foundation piling and sheet pile retaining wall works have been successfully completed. Excavation for the pile caps is currently underway, along with the installation of pile cap formwork and rebar.

As we begin the New Year 2026, we wish everyone a year filled with good health, harmony, growth in the Dhamma and smooth progress in all endeavors.

Photos from Ariya Vihara Building Project's post 23/10/2025

The RIBI road premix is completed and under inspection.

Want your place of worship to be the top-listed Place Of Worship in Shah Alam?
Click here to claim your Sponsored Listing.

Category

Telephone

Address


No. 37-1 & 37-2, Jalan Nautika B U20/B, Seksyen U20, Pusat Komersil TSB, Sg Buloh
Shah Alam
40160