Lesotho Lowlands Water Development Project Phase II
Lesotho Lowlands Water Development Project Phase II (LLWDP-II) is aimed at improving supply of potab
10/06/2026
Golden sun of Ha Sekoati, Mafeteng
09/06/2026
Update on the PitsengβHa Setene Power Line
The electrical power supply to the Ha Setene Water Treatment Works (WTW) is sourced from the Pitseng Substation.
Ministry of Natural Resources Lesotho
European Union in Lesotho
European Investment Bank
ReNOKA
02/06/2026
Happy Birthday Her Majesty Queen 'Masenate Mohato Seeiso! π
Wishing Your Majesty good health, happiness, and many more blessed years. May your special day be filled with joy and celebration.
Happy Birthday, Your Majesty!
02/06/2026
Tsehlanyane Adit Pipeline Installation Progress!!
Work is progressing on the installation of the bulk water supply pipeline inside the Tsehlanyane Adit. The pipeline will convey water released from the Lesotho Highlands Water Project (LHWP) during the low-flow season to support water supply in Hlotse, Maputsoe, and villages along the route.
This important infrastructure will contribute to improved water security and reliable access to water for communities and industries in the Lowlands.
Ministry of Natural Resources Lesotho
European Union in Lesotho
Lesotho Lowlands Water Development and Sanitation Project Phase III
ReNOKA
29/05/2026
28/05/2026
VACANCY ANNOUNCEMENT β HEALTH AND SAFETY SPECIALIST
The Lesotho Lowlands Water Development Project Phase II (LLWDP-II) invites applications from suitably qualified Basotho nationals for the position of:
πΉ Health and Safety Specialist
Interested candidates are encouraged to refer to the attached vacancy advertisement for full details on qualifications, requirements, and application procedures.
Ministry of Natural Resources Lesotho
Lesotho Lowlands Water Development and Sanitation Project Phase III
European Union in Lesotho
26/05/2026
WORLD BANK IMPLEMENTATION SUPPORT MISSION (ISM) β LLWDP II
The World Bank conducted an Implementation Support Mission (ISM) for the Lesotho Lowlands Water Development Project Phase II (LLWDP II) from 18β22 May 2026. During the mission, the World Bank delegation held consultative meetings with the following key stakeholders:
i. The Ministry of Natural Resources (MoNR);
ii. The Commissioner of Water (CoW);
iii. The Lesotho Lowlands Water Development Project Phase II (LLWDP II) Project Implementation Unit (PIU); and
iv. iv. The Water and Sewerage Company (WASCO).
The objectives of the mission were to:
1. Assess overall progress on project implementation since the previous support mission conducted in November 2025 and the subsequent technical mission held in February 2026;
2. Review project fiduciary compliance, with particular focus on financial management and procurement; and
3. Discuss preparations for the Implementation Completion and Results Report (ICR), including agreement on key actions required before project closure on 31 December 2026.
Based on the implementation progress observed during the mission, the Project remained on track to achieve its development objectives. The overall assessment by the World Bank was that project implementation was satisfactory. These engagements facilitated discussions on overall project implementation progress, fiduciary compliance, implementation challenges, and the key actions required in preparation for project closure and completion reporting.
The mission noted that the three key contracts were nearing full completion, with physical progress recorded at 100%, 99.8%, and 98.9%, respectively; W/04 β Construction of the Bulk Water Transmission system and Reservoirs, W/05 β Distribution networks (Hlotse, Khanyane & Ha Lesiamo), and W/06 β Construction of Distribution Systems (Tsikoane, Maputsoe & Mpharane).
The World Bank delegation comprised Ms. Palesa Mokorosi (Senior Water Resources Management Specialist), Mr. F**k Chuan Eng (Lead Water Supply and Sanitation Specialist), Mr. Zvikomborero Hoko (Water and Sanitation Engineer β Consultant), with the participation of Mr. Josses Mugabi (Practice Manager) and Mr. Lubabalo Luyaba (Senior Water Specialist).
Ministry of Natural Resources Lesotho
European Union in Lesotho
Lesotho Lowlands Water Development and Sanitation Project Phase III
ReNOKA
Hon. Mohlomi Moleko Minister of Natural Resources giving a keynote address during the Sod Turning Ceremony at Ha Katamelo, Botha Bothe.
15/05/2026
M*f. 'Mamanamolela Mopeli, Chieftainess, Botha Bothe district making remarks during the Sod turning Ceremony at Ha Katamelo, Botha Bothe
Click here to claim your Sponsored Listing.
Category
Contact the organization
Telephone
Website
Address
Block C, Sentinal Park, 15 United Nations Road
Maseru
100
Opening Hours
| Monday | 08:00 - 16:30 |
| Tuesday | 08:00 - 16:30 |
| Wednesday | 08:00 - 16:30 |
| Thursday | 08:00 - 16:30 |
| Friday | 08:00 - 16:30 |