Civil Engineering Resource

Civil Engineering Resource

Share

Contact information, map and directions, contact form, opening hours, services, ratings, photos, videos and announcements from Civil Engineering Resource, Akure.

This page is about the basic and advanced knowledge on Civil Engineering: Soil and Foundation; Transportation and Highway; Water and Environmental; and Structural and Building

Photos from Civil Engineering Resource's post 12/09/2025

The hardened concrete of the base of raft foundation after stripping

12/09/2025

The hardened concrete of the base of the raft foundation

Photos from Civil Engineering Resource's post 04/09/2025

Formwork for an 11.5 X 11.5 m2 Raft Foundation

04/09/2025

Formwork for Raft Foundation

Formwork shall be designed and constructed to remain sufficiently rigid during concrete placement, and compaction (vibration) of concrete shall be such as to prevent loss of slurry from the concrete. Dirts: dusts, sawdust, and shavings must be removed from formworks, and appropriate release agent must be applied during installation for ease of removal of formwork.

Stripping of Concrete
Formwork shall not be removed untill the concrete has achieved a strength of at least twice the stress to which the concrete may be subjected at the time of removal.

Photos from Civil Engineering Resource's post 02/09/2025

Construction of raft foundation with beams and the pedestals.

That's the reinfircement bars arrangement for a 300 m3, 16 m high elevated water tank.
The foundation is in a saturated soil condition within a water bearing formation.
There is continuous dewatering and lateral earth protection against Earth collapse.

30/08/2025

Site Investigation

An investigation of project site is essential for judging its suitability for proposed engineering works, and for preparing adequate and economic designs.

Site investigation is also necessary for analysing the safety or causes of failures of existing structures, for selecting construction materials, and for deciding upon the construction methods to be applied.

In general, the purpose of site investigation is to obtain necessary information about the soil and hydrological conditions, and to know the engineering properties of the soil which will be affected.

The methods of investigation depends largely on the engineering project and the site.

Join us in the online lectures !

Share the information!

Photos from Civil Engineering Resource's post 29/05/2024

Construction of 132/33 kV Tower Plinth in a 132 /33 kV Substation

After the soil test is carried out to know the bearing capacity of the foundation soil, the tower plinth is designed. The steel tensile stress and concrete mix design are carried out.

In a 132/33 kV Substation, the tower is arranged in a bay. A bay consists of two towers structures connected by a beam structure at a height of about 10 - 13 m
Each tower has four structural steel legs. Each leg is held in place by four or three anchor bolts

Below is the procedure for constructing the Tower Plinth in a Substation.

1. From the Substation layout drawing, the Surveyor uses the total station to set out the tower points. The plinth center ls very important.

2. After setting out of the tower points, the excavation begins. Before the excavation is carried out, the finished grade level value is noted and the Top of Concrete (TOC) value is noted and used as reference for excavation height. The level instrument is used to determine the heights.

The excavation is usually carried out with excavator unless the soil needs Pile foundation.

3. After excavation, the pit is cut to appropriate size: length, width, and height. It is then compacted.

4. With the aid of the center lines: x and y, and the conical and bubble plum, the center lines of the plinth are fixed in the pit

5. The blinding of the base follows with the casting of the PCC - plain cenent concrete.

6. The PCC is cured, the concrete casting of the base follows.The positions of the reinforcements are marked on the PCC in the pit and reinforcements are placed with proper bracing.

7. The base of the plinth is cast with dense graded concrete and well vibrated. Then, properly cured.

8. The fixing of the formwork follows. The height of the plinth is usually from 1.5 - 1.9 m. The formwork must be strong and properly braced.

The Engineer on site must request for the anchor bolts details for him to fabricate the template.The template could be fabricated with angle bars or 16 mm rods

9. Concrete casting of the plinth. The concrete mix must be a dense graded mix to avoid cracking in future due to extreme weather conditions..Before casting is carried out, the template and anchor bolts must be properly fixed using the intially established centre lines During casting, concrete must be well vibrated. It is advisable to cast one half each leg first , then return to complete.This will avoid the swaying of the plinths and the shape will be maintained. After concrete casting then, it is well cured.

If you find this educative, please, share.

Photos from Civil Engineering Resource's post 28/05/2024

Construction of 60 MVA Transformer Plinth in a 132 /33 kV Substation

After the soil test is carried out to know the bearing capacity of the foundation soil, the transformer Plinth is designed.

Below is the procedure for constructing the transformer Plinth in a Substation.

1. From the Substation layout drawing, the Surveyor uses the total station to set out the points. The plinth center line is very important. There are usually three plinths having the same base.

2. After setting out of the plinth, the excavation begins. Before the excavation is done, the finished grade level value is noted and the Top of concrete (TOC) value is noted and used as reference for excavation height. The level instrument is used to determine the heights.

The excavation is usually done with the excavator unless the soil needs Pile foundation.

3. After excavation, the pit is cut to appropriate size: length, width, and height.

4. With the aid of the center lines: x and y, and the conical and bubble plum, the center lines of the plinths are fixed in the pit

5. The blinding of the base follows with the casting of the PCC - plain cenent concrete.

6. The PCC is cured, the concrete casting of the base follows.The positions of the reinforcements are marked on the PCC in the pit for the three pillars and the reinforcements are placed with proper bracing.

7. The base of the plinth is cast with dense graded concrete and well vibrated. Then, properly cured.

8. The fixing of the formwork follows. The height of the plinth is usually from 2 m and above. The formwork must be strong and properly braced The anchor steel plates must be properly fixed in position.

9. Concrete casting of the plinth - there are three pillars. It is advisable to cast the center pillar one half first , then cast the side pillars one half each, then return to complete the center and the side pillars. This will avoid the swaying of the pillars and the shape will be maintained. After concrete casting the, it is cured.

10. The concrete casting of the oil catchment area

Want your university to be the top-listed University in Akure?
Click here to claim your Sponsored Listing.

Telephone

Website

Address

Akure