18/06/2026
Step 1: Site Leveling and Debris Removal
Remove all , rocks, and unwanted materials from the surface.
Level the ground to create a uniform and stable working area.
16/06/2026
Today’s delivery from Slab Decor with crane service. 🚚🏗️
10/06/2026
Laying of margelles in progress around the pool area with careful alignment and spacing to ensure a clean and elegant finish.
Preparation of the surface has been completed to provide a strong and durable base before installation. Each margelle is being placed with precision to guarantee stability, safety, and long-lasting quality while enhancing the overall appearance of the swimming pool area.
Early morning delivery of slab decor at Veranda Pointe aux Biches Hotel with crane facilities arranged for safe unloading and handling of materials.
04/06/2026
Before & after the work ✨
Complete transformation with quality slab installation and finishing. 🧱🔨
03/06/2026
Finished Work
The coloured slab laying works have now been successfully completed as per the client’s requested design and specifications.
The area has been transformed into a clean, modern, and visually attractive space with a professionally arranged pattern of coloured slabs, giving the surface both elegance and durability.
All slabs were carefully aligned and properly installed to ensure a strong, level, and long-lasting finish.
Attention was given to every detail throughout the project, from site preparation to the final laying works, to achieve a neat and high-quality result.
Another project completed with dedication, precision, and customer satisfaction as our priority.
🎥 Work in progress — transforming the ground step by step into a solid and durable surface for the future slab installation. 🏗️✨
Every phase brings us closer to the final result. 💪🚧
03/06/2026
Phase 2
Leveling of the ground using a mixture of cement and rock sand to create a solid and durable base for the future laying of slabs. The surface is carefully prepared to ensure proper alignment, stability, and long-lasting results for the slab installation works.
Bobcat is currently leveling the land surface to ensure a smooth, even, and well-prepared area for the upcoming works. 🚧
02/06/2026
Land leveling in progress 🚧
Work is currently being carried out to prepare and level the surface for upcoming slab installation works.
Click here to claim your Sponsored Listing.
Category
Contact the business
Website
Address
Grand Baie
Opening Hours
| Monday | 08:00 - 17:00 |
| Tuesday | 08:00 - 17:00 |
| Wednesday | 08:00 - 17:00 |
| Thursday | 08:00 - 17:00 |
| Friday | 08:00 - 17:00 |
| Saturday | 08:00 - 17:00 |
| Sunday | 08:00 - 13:00 |